Project Description
The new computer-controlled conveyor belt is an exciting project that moves and positions
items on the conveyor belt within <1 millimeter. The project will produce a new system for
future installations, and for replacement of those in the field, at a low cost. The computer
controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems
installed in factories. The new system is also easier to update with future technologies.
The Project Priority Matrix for the Conveyor Belt Project (CBP) is:
Table A2.9 has been developed for you to use in completing the project exercises.
Assignment P1:
Develop the WBS outline using the software available to you.
Part 2 (7 Marks)
Use your file from Part 1 and the information provided below to complete this exercise. (See
Table A2.10.)

  1. Each work package will represent an activity.
  2. The project begins January 4, 2021.
  3. The following holidays are observed: January 1, Memorial Day (last Monday in May), July
    4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November),
    December 25 and 26 (Christmas Holiday)
  4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls
    on a Sunday, then Monday will be given as a day off.
  5. The project teams work eight-hour days, Monday through Friday.
    Assignment P2:
    Construct a network schedule for the conveyor belt project and prepare a memo that
    addresses the following questions:
  6. When is the project estimated to be completed? How long will the project take?
  7. What is the critical path(s) for the project?
  8. Which activity has the greatest amount of slack?
  9. How sensitive is this network?
  10. Identify two sensible milestones and explain your choices.
  11. Include the following printouts:
    a) A Gantt chart.
    b) A network diagram highlighting the critical path.
    c) A schedule table reporting ES, LS, EF, LF, and slack for each activity.
    Part 3 (8 Marks)
    Remember the old saying, “A project plan is not a schedule until resources are committed.”
    This exercise illustrates this subtle, but very important, difference.
    Part A
    Using your files from Part 2 input resources and their costs if you have not already done so.
    All information is found in Tables A2.10 and A2.11.
    Assignment P3:
    Prepare a memo that addresses the following questions:
  12. Which if any of the resources are overallocated?
  13. Assume that the project is time constrained and try to resolve any overallocation problems
    by leveling within slack. What happens?
  14. What is the impact of leveling within slack on the sensitivity of the network? Include a
    Gantt chart with the schedule table after leveling within slack.
  15. Assume the project is resource constrained and resolve any overallocation problems by
    leveling outside of slack. What happens? What are the managerial implications?
    Note: No splitting of activities is allowed.
    Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.
    Part 4 (4 Marks)
    Assignment P4:
    Based on the file created at the end of Part 3, prepare a memo that addresses the following
    questions:
  16. How much will the project cost?
  17. What does the cash flow statement tell you about how costs are distributed over the life
    span of the project?
    Include a monthly cash flow and a cost table for the project.
    Once you are confident that you have the final schedule, save the file as a baseline.
    Hint: Save a backup file just in case without baseline!
    Part 5 (8 Marks)
    Prepare status reports for the first quarter of the project given the information provided here.
    This requires saving your resource schedule as a baseline and inserting the appropriate status
    report date in the program. Assume that no work has been completed on the day of the status
    report.
    Assignment P5:
    Your status report should include a table containing the PV, EV, AC, BAC, EAC, SV, CV,
    and CPI for each activity and the whole project. The report should also address the following
    questions:
  18. How is the project progressing in terms of cost and schedule?
  19. What activities have gone well? What activities have not gone well?
  20. What do the PCIB and PCIC indicate in terms of how much of the project has been
    accomplished to date?
  21. What is the forecasted cost at completion (EACf)? What is the predicted VACf?
  22. Report and interpret the TCPI for the project at this point in time.
    Try to present the above information in a form worthy of consideration by top management.
    Include a Tracking Gantt chart with the report.
    First Quarter, April 1, 2021
    Table A2.12 summarizes the information regarding activities accomplished to date.

Sample Solution

Socialism is a stopped political hypothesis. It has never been drilled in the United States. It is typically positioned in a truly unsteady world of politics like Cuba and China. A typical agreement on socialism is this is an excellent thought, however in all actuality it isn’t excessively acceptable. Individuals consistently prefer to settle on choices themselves. Karl Marx is known as the “father” of Communism. He composed the “Socialist Party Declaration” in 1848, he was therefore perceived. “Network” is a shapeless term on the off chance that it is utilized equivalently with “gathering”. People are individuals from numerous gatherings and are in this manner part of numerous networks. School is a network. The people group is a network. The city is a network. The expert is a network. The congregation is a network. In this way, schools are a) networks, b) substances in bigger networks, and c) littler networks. That implies excessively, the network has neither rhyme nor reason. Schools talk about well about their associations with the network. This shows the school is not the same as the network. For sure, schools exist in covering networks and can go about as networks themselves. The people group is a gathering of individuals who are identified with one another and share regular qualities. Geology is neither a network, a part nor an occurrence. A gathering of individuals in a network with a typical point (eg history, values, devotion, shared objectives). In this system, network individuals are given participations (eg “comparative”) characterized by individuals’ proprietorship dependent on outside definition standards identified with network capacities (eg as school of understudies) and individual trust for enrollment Recognition) is incorporated. Individuals with political or social issues 2 Citizenship is the way that the basic association among individuals is more noteworthy than that of enormous families (counting relatives), and resident’s dynamic, investment, administration and It is the standard of authoritative administration. , Mechanism and ProcessThe thought that the network affects the arrangement of character is the way to Pythia Peay’s article “Soul Searching” and Winona LaDuke’s meeting. “The two creators who keep up the network introduced comparable perspectives and alternate points of view by living in the network and turning out to be individuals from the network and influencing individuals in the network. I experienced a month to month or yearly get-together, and they accounted for themselves as networks: the Network Summit Community, the TEDx Community, the SxSW Community and the New York Tech Party Community. I have asked myself as an examination network and as a member in a large number of these exercises: are these exercises really a network? What is the limit between normal social occasions/get-togethers/gatherings and the network? The greatest contrast is that the occasion is extremely useful for individuals to construct an individual 1: 1 relationship. There might be significantly more. Then again, the intensity of the network lies in aggregate personality. We see ourselves as a gathering having a place with one gathering and we confide in one another over the normal level. Our exercises are little, however the network is huge. As an expansion of the occasion understanding, I made a Slack people group. Emotionally supportive network consistently. Any female business visionary or financial specialist is welcome. Despite the fact that the historical backdrop of this network is just three months, intrigue and cooperation was magnificent. As we become familiar with the necessities and requirements of this network, we will proceed to adjust and develop and keep on giving assets, data and availability on the web. How about we join our locale. Our message network has more than 7,500 individuals, and we have another Discord channel with in excess of 1,000 individuals. On the off chance that you need to enroll on Slack (12,000 clients and engineer network landing page), if you don’t mind use @ thisis to send email address to wire. The enlistment of the Public Slack is as yet shut. For increasingly significant declarations on Enigma, follow this blog and our Twitter. At the point when we assemble understandings and stages to enable us to develop, our prosperity is firmly identified with our locale backing and awareness. We will effectively share the most recent data on the network and news and improvement consistently. You can assist us with promoting our undertaking and vision on your system. The expression “network” is regularly used to allude to where individuals live and to all individuals living there. A people group may likewise allude to a gathering of individuals who perceive themselves as networks since encounters, histories, values, religion, culture, and so forth are shared. The chairman can consider his town a network, however in many urban areas there are a few self-characterized networks – the Italian-American people group, the gay network, the Jewish people group, the African American people group, the business network I don’t accept that all individuals from these networks have a similar view or act a similar way, yet I think there is something in the same way as different individuals from the network.>

Is this question part of your Assignment?

We can help

Our aim is to help you get A+ grades on your Coursework.

We handle assignments in a multiplicity of subject areas including Admission Essays, General Essays, Case Studies, Coursework, Dissertations, Editing, Research Papers, and Research proposals

Header Button Label: Get Started NowGet Started Header Button Label: View writing samplesView writing samples