Chapter Thirteen

Progress and Performance Measurement and Evaluation

131

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

132

Where We Are Now

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

132

Project Management 6e.

Learning Objectives

Identify the four steps for controlling a project

Utilize a tracking Gantt to monitor time performance

Understand and appreciate the significance of earned value

Calculate and interpret cost and schedule variance

Calculate and interpret performance and percent indexes

Forecast final project cost

Identify and manage scope creep

133

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Chapter Outline

13.1Structure of a Project Monitoring Information

System

13.2The Project Control Process

13.3Monitoring Time Performance

13.4Development of an Earned Value

Cost/Schedule System

13.5Developing a Status Report: A Hypothetical

Example

13.6Indexes to Monitor Progress

13.7Forecasting Final Project Cost

13.8Other Control Issues

134

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

135

Structure of a Project Monitoring Information System

Creating a project monitoring system involves determining:

What data to collect

How, when, and who will collect the data

How to analyze the data

How to report current progress to management

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

135

Project Management 6e.

136

Project Monitoring Information System

Information System Structure

What Data Are Collected?

Current status of project (schedule and cost)

Remaining cost to compete project

Date that project will be complete

Potential problems to be addressed now

Cost and/or schedule overruns and the reasons for them

Forecast of overruns at time of project completion

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

136

Project Management 6e.

137

Project Monitoring Info. System (contd)

Information System Structure (contd)

Collecting Data and Analysis

Who will collect project data?

How will data be collected?

When will the data be collected?

Who will compile and analyze the data?

Reports and Reporting

Who will receive the reports?

How will the reports be transmitted?

When will the reports be distributed?

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

137

Project Management 6e.

138

Project Progress Report Format

Progress since last report

Current status of project

Schedule

Cost

Scope

Cumulative trends

Problems and issues since last report

Actions and resolution of earlier problems

New variances and problems identified

Corrective action planned

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

138

Project Management 6e.

139

The Project Control Process

Control

The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action

Project Control Steps

Setting a baseline plan

Measuring progress and performance

Comparing plan against actual

Taking action

Tools for Monitoring Time Performance

Tracking Gantt chart

Control chart

Milestone schedules

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

139

Project Management 6e.

1310

Baseline and Tracking Gantt Charts

FIGURE 13.1

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1310

Project Management 6e.

1311

Project Schedule Control Chart

FIGURE 13.2

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1311

Project Management 6e.

Development of an Earned Value Cost/Schedule System

Time-Phase Baseline Plan

Corrects the failure of most monitoring systems to connect a projects actual performance to its schedule and forecast budget.

Systems that measure only cost variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule.

Earned Value Cost/Schedule System

An integrated project management system based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs

1312

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1312

Project Management 6e.

1313

Glossary of Terms

TABLE 13.1

EV
Earned value for a task is simply the percent complete times its original budget. Stated differently, EV is the percent of the original budget that has been earned by actual work completed. [BCWPbudgeted cost of the work performed].

PV
The planned time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources scheduled in a time-phased cumulative baseline [BCWSbudgeted cost of the work scheduled].

AC
Actual cost of the work completed. The sum of the costs incurred in accomplishing work. [ACWPactual cost of the work performed].

CV
Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV AC.

SV
Schedule variance is the difference between the earned value and the baseline line to date where SV = EV PV.

BAC
Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.

EAC
Estimated cost at completion.

ETC
Estimated cost to complete remaining work.

VAC
Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1313

Project Management 6e.

1314

Developing an Integrated Cost/Schedule System

Define the work using a WBS.

Scope

Work packages

Deliverables

Organization units

Resources

Budgets

Develop work and resource schedules.

Schedule resources to activities

Time-phase work packages into a network

Develop a time-phased budget using work packages included in an activity. Accumulate budgets (PV).

At the work package level, collect the actual costs for the work performed (AC). Multiply percent complete times original budget (EV).`

Compute the schedule variance (EV-PV) and the cost variance (EV-AC).

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1314

Project Management 6e.

1315

Project Management Information System Overview

FIGURE 13.3

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1315

Project Management 6e.

1316

Development of Project Baselines (contd)

Rules for Placing Costs in Baselines

Costs are placed exactly as they are expected to be “earned” in order to track them to their point of origin.

Percent Complete Rule

Costs are periodically assigned to a baseline as units of work are completed over the duration of a work package.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1316

Project Management 6e.

1317

Development of Project Baselines (contd)

Purposes of a Baseline (PV)

An anchor point for measuring performance

A planned cost and expected schedule against which actual cost and schedule are measured

A basis for cash flows and awarding progress payments

A summation of time-phased budgets (cost accounts as summed work packages) along a project timeline

What Costs Are Included in Baselines?

Project direct overhead costs: labor, equipment, materials

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1317

Project Management 6e.

1318

Methods of Variance Analysis

Comparing Earned Value with:

The expected schedule value

The actual costs

Assessing Status of a Project

Required three data elements

Planned cost of the work scheduled (PV)

Budgeted cost of the work completed (EV)

Actual cost of the work completed (AC)

Calculate schedule and cost variances

A positive variance indicates a desirable condition, while a negative variance suggests problems or changes that have taken place.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1318

Project Management 6e.

1319

Methods of Variance Analysis

Cost Variance (CV)

Indicates if the work accomplished costs more or less than was planned at any point in the project.

Schedule Variance (SV)

Presents an overall assessment in dollar terms of the progress of all work packages in the project scheduled to date.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1319

Project Management 6e.

1320

Cost/Schedule Graph

FIGURE 13.4

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1320

Project Management 6e.

1321

Earned-Value Review Exercise

FIGURE 13.5

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1321

Project Management 6e.

1322

Developing A Status Report:A Hypothetical Example

Assumptions

Each cost account has only one work package, and each cost account will be represented as an activity on the network.

The project network early start times will serve as the basis for assigning the baseline values.

From the moment work an activity begins, some actual costs will be incurred each period until the activity is completed.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1322

Project Management 6e.

1323

Work Breakdown Structure with Cost Accounts

FIGURE 13.6

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1323

Project Management 6e.

1324

Digital Camera Prototype Project Baseline Gantt Chart

FIGURE 13.7

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1324

Project Management 6e.

1325

Digital Camera Prototype Project Baseline Budget ($000)

FIGURE 13.8

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1325

Project Management 6e.

1326

Digital Camera Prototype Status Reports: Periods 13

TABLE 13.2

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1326

Project Management 6e.

1327

Digital Camera Prototype Status Reports: Periods 4 & 5

TABLE 13.2 (contd)

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1327

Project Management 6e.

1328

Digital Camera Prototype Status Reports: Periods 6 & 7

TABLE 13.2 (contd)

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1328

Project Management 6e.

1329

Digital Camera Prototype Summary Graph ($000)

FIGURE 13.9

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1329

Project Management 6e.

1330

Digital Camera Project-Tracking Gantt Chart Showing StatusThrough Period 7

FIGURE 13.10

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1330

Project Management 6e.

1331

Project Rollup End Period 7 ($000)

FIGURE 13.11

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1331

Project Management 6e.

1332

Indexes to Monitor Progress

Performance Indexes

Cost Performance Index (CPI) = EV/AC

Measures the cost efficiency of work accomplished to date.

Scheduling Performance Index (SPI) = EV/PV

Measures scheduling efficiency to date.

Percent Complete Indexes

Indicate how much of the work accomplished represents of the total budgeted (BAC) and actual (AC) dollars to date.

Percent Complete Index Budgeted Costs (PCIB) = EV/BAC

Percent Complete Index Actual Costs (PCIC) = AC/EAC

Management Reserve Index (MRI) = CV/MR

Reflects the amount of Management Reserve (MR) that has been absorbed by cost over-runs.

Is popular in the construction industry.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1332

Project Management 6e.

1333

Interpretation of Indexes

TABLE 13.3

Index
Cost (CPI)
Schedule (SPI)

>1.00
Under cost
Ahead of schedule

=1.00
On cost
On schedule

<1.00 Over cost Behind schedule

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1333

Project Management 6e.

1334

Indexes Periods 17

FIGURE 13.12

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1334

Project Management 6e.

1335

Additional Earned Value Rules

Rules applied to short-duration activities and/or small-cost activities

0/100 percent rule

Assumes 100% of budget credit is earned at once and only when the work is completed.

50/50 rule

Allows for 50% of the value of the work package budget to be earned when it is started and 50% to be earned when the package is completed.

Ruled used gates before the total budgeted value of an activity can be claimed

Percent complete with weighted monitoring gates

Uses subjective estimated percent complete in combination with hard, tangible monitoring points.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1335

Project Management 6e.

1336

Forecasting Final Project Cost

Methods used to revise estimates of future project costs:

Revised estimated cost at completion (EACre)

Allows experts in the field to change original baseline durations and costs because new information tells them the original estimates are not accurate.

Forecasting cost at completion (EACf)

Uses actual costs-to-date plus an efficiency index to project final costs in large projects where the original budget is unreliable.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1336

Project Management 6e.

1337

Forecasting Models: EACre and EACf

The equation for

The equation for

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1337

Project Management 6e.

1338

Forecasting Final Project Cost (contd)

Method supplemented to the estimate at completion (EACf) computation:

To Complete Performance Index (TCPI)

Measures the amount of value each remaining dollar in the budget must earn to stay within the budget.

A ratio less than 1.00 indicates an ability to complete the project without using all of the remaining budget.

The equation for

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1338

Project Management 6e.

1339

Monthly Status Report

EXHIBIT 13.1

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1339

Project Management 6e.

1340

Trojan Nuclear Plant Decommissioning Earned Value Status Report

EXHIBIT 13.2

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1340

Project Management 6e.

1341

Other Control Issues

Issues In Maintaining Control of Projects

Scope Creep

Baseline Changes

Technical Performance Measurement

Data Acquisition Costs and Problems

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1341

Project Management 6e.

1342

Scope Changes to a Baseline

FIGURE 13.13

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1342

Project Management 6e.

1343

Conference Center WiFi ProjectCommunication Plan

FIGURE 13.14

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1343

Project Management 6e.

1344

Key Terms

Baseline budget

Budget at completion (BAC)

Control chart

Cost performance index (CPI)

Cost variance (CV)

Earned value (EV)

Estimated Cost at CompletionForecasted (EACf)

Estimated Cost at CompletionRevised Estimates (EACre)

Percent complete indexbudget costs (PCIB)

Percent complete indexactual costs (PCIC)

Schedule performance index (SPI)

Schedule variance (SV)

Scope creep

To complete performance index (TCPI)

Tracking Gantt chart

Variance at completion (VAC)

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

1344

Project Management 6e.

The post Chapter13-ProgressandPerformanceMeasurementandEvaluation.pptx appeared first on essaypages.

Is this question part of your Assignment?

We can help

Our aim is to help you get A+ grades on your Coursework.

We handle assignments in a multiplicity of subject areas including Admission Essays, General Essays, Case Studies, Coursework, Dissertations, Editing, Research Papers, and Research proposals

Header Button Label: Get Started NowGet Started Header Button Label: View writing samplesView writing samples