the position of Project Executive for a national general contracting company, General Contractor, Inc. (“GCI”).
in charge of the western region and have
assumed responsibility over a new 300 room hotel/resort project in California. The HVAC mechanical subcontractor, Best Mechanical, Inc. (“Best”), has not shown up for
work in over one week. Best did not provide a performance bond. No written form of agreement was executed between GCI and Best. Your Project Manager has sent emails,
texts, and voice messages to Best. Best’s response was, “I am not making money on the project so, unless you pay me 35% more, I cannot continue.” Best also stated
that the mechanical drawings and specifications prepared by the owner’s mechanical engineer were horrible, unbuildable, and defective (likely an overstatement). The
mechanical work is on the critical path and the Project is being delayed. You have received notices of impacts from the Project delay from other subcontractors and
the owner.
c. Prepare a notice letter to the owner requesting a change order for an extension of time and damages due to delays caused by the defective mechanical engineering
drawings/specifications.
d. Compose a request for proposal (max 2 pages) and draft subcontract agreement (max 5 pages) for the replacement HVAC mechanical subcontractor.
e. Write up a written protocol (max 1 page) to GCI’s project management team and estimating department that creates a cost code to track additional costs incurred
following Best’s default and tracks delays to the schedule.

Is this question part of your Assignment?
We can help
Our aim is to help you get A+ grades on your Coursework.
We handle assignments in a multiplicity of subject areas including Admission Essays, General Essays, Case Studies, Coursework, Dissertations, Editing, Research Papers, and Research proposals
Header Button Label: Get Started NowGet Started Header Button Label: View writing samplesView writing samples